Problems:

Can anyone give the right solution?

Which column in Microsoft Project defines the precedence relationships among the​ activities?
A. Order.
B. Relations.
C. Predecessors.
D. Successors.

7 5 3
5,380 points

1 Answer

0 votes

Solutions:

Let me try to help you with your query.

The correct answer is: Predecessors.
  
Hope this might help you.

7 4 2
10,530 points

Related questions

0 votes
1 answer 16 views
16 views
Problem: Can anyone brief the right solution? Which column in Microsoft Project defines the precedence relationships among the? activities? A.Predecessors B.Order C.Successors D.Relations
asked Feb 17 maddi86 5.4k points
0 votes
1 answer 38 views
38 views
Problem: Which of the following is the online storage system affiliated with a Microsoft account? A) iCloud B) Chrome C) OneDrive D) iOS
asked Apr 18 ArifulIslam 5.7k points
0 votes
1 answer 16 views
16 views
Problem: All of the following are examples of activities performed by an operating system EXCEPT:?
asked Aug 4 ArifulIslam 5.7k points
0 votes
2 answers 23 views
23 views
Problem: Can any one help me in this query? What are the paths which opens the computer management tool in windows 10?
asked Feb 19 maddi86 5.4k points
0 votes
1 answer 20 views
20 views
Problems: Can anyone give the right solution? In which of the following situations would restoring from a backup be the best option? (Select Two.) A. You need to restore several word processing files that were accidentally deleted from My Documents. B. You recently ... a new application and now the system behaves erratically. E. You need to restore a Windows system after a hard drive failure.
asked Feb 14 maddi86 5.4k points