Problem:

Can anyone brief the right solution?

Which column in Microsoft Project defines the precedence relationships among the? activities?
A.Predecessors
B.Order
C.Successors
D.Relations

7 5 3
5,380 points

1 Answer

0 votes

Solution:

It's very simple as  answer is : Predecessors

Explanation:
The predecessor’s column defines the precedence relationships among the activities in a Microsoft project. The precedence diagram is implemented to show task dependencies (finish to start, start to start, finish to finish, start to finish).

This might help you.

7 4 2
10,530 points

Related questions

0 votes
1 answer 24 views
24 views
Problems: Can anyone give the right solution? Which column in Microsoft Project defines the precedence relationships among the​ activities? A. Order. B. Relations. C. Predecessors. D. Successors.
asked Feb 14 maddi86 5.4k points
0 votes
1 answer 20 views
20 views
Problem: I am little bit confused, which statement is true? Which of the following statements is true of Extensible Markup Language (XML)? XML documents are utilized for displaying graph structures. XML documents can handle data in graphs with multiple root ... as well as doing nothing without having any predefined tags. XML tags represent the kind of content being posted and transmitted
asked Feb 19 maddi86 5.4k points
0 votes
1 answer 38 views
38 views
Problem: Which of the following is the online storage system affiliated with a Microsoft account? A) iCloud B) Chrome C) OneDrive D) iOS
asked Apr 18 ArifulIslam 5.7k points
0 votes
1 answer 23 views
23 views
Problem: Can anyone help me? which permissions are assigned directly to a file or folder?
asked Feb 19 maddi86 5.4k points
0 votes
1 answer 4 views